Tuesday, November 1 We have begun building at the Knight house (see below). We need workers!
October 19 Insulation for Walls
October 20-21 Sheetrock (Hang and Finish)
October 19-26 Exterior Siding
October 22 Install baseboard trim.
October24-26 Paint
October 25-26 Install Cabinets and Counter Tops
October 26-29 Install Laminate Flooring
October 28/29 Landscaping and Planting
October 31-Nov. 4 Furnishings for Rooms
Target: Move-In Celebration...November 8...10:00 a.m.